Traffic Impacts

Intermittent Flagging Throughout the Project, from 0.5 km east of Essex Road 23 easterly to 1.0 km east of Essex Road 34, March 2025 to December 2025

​​​Please be advised of the following closures: ​​

​

​Graham Side Road from Highway 3 to 300m north of Highway 3

Planned Closure: October 2, 2025 - November 13, 2025 (on dates weather permitting)

​

This closure is required to facilitate reconstruction of the Highway 3 and Graham Side Road intersection.

​

Detour routes will be signed  ten business days prior to this closure.

​

Highway 3 and Essex Road 29, north side of Highway 3

Planned Closure: October 14 - October 31, 2025 (on dates weather permitting) 

 

The initial closure will be Essex Road 29 from South Talbot Road to 94 Division Road north. There will be no through traffic permitted in the construction area.

​

There will not be a signed detour for this closure. Signage will be in place directing traffic to use alternate routes.

​