top of page

Frequently Asked Questions

We will continue to update this page with Frequently Asked Questions. To submit a question, please contact the project team through the Contact Us page.

General Project Information

 

What are the proposed improvements of the Highway 3 Widening Project?

Key components of the proposed improvements include:

  • Design and construction of a new 4-lane mainline cross section of approximately 15.6 km of Highway 3 mainline with a 15 m depressed median, with two new lanes being constructed for the eastbound direction and resurfacing and reconstruction of the existing lanes for the westbound direction

  • Reconfiguration of five (5) intersections along Highway 3 including associated illumination and auxiliary lanes

  • Closure and realignment of select side roads

  • Extension, rehabilitation, construction and abandonment of structural culverts

  • All infrastructure including environmental, drainage, traffic signal, illumination, roadside safety, and noise Works.

 

Who is GIP HWY 3 Inc.?

GIP HWY 3 Inc. is comprised of GIP Paving Inc.; Construction Contractor, Dillon Consulting Limited; Lead Designer, and WSP (Golder Associates Ltd.); Foundations and Pavement Designers. GIP HWY 3 Inc. was selected by The Ministry of Transportation Ontario (MTO) and Infrastructure Ontario (IO) to design, build and finance the Highway 3 Widening Project.

 

What are the benefits of this project?

Benefits of the Highway 3 Widening Project include:

  • Improvements to Hwy 3 from 1.2km east of Essex Road 23 to 1.1km east of
    Essex Road 34

  • More effective movement of people and goods, both locally and regionally.

 

GIP HWY 3 Inc. also estimates that approximately 60+ workers will be on site during peak construction periods.  With most workers residing in the Greater Essex County Area, local economic benefits and employment opportunities are also anticipated.

​

Construction

 

When will construction begin?

Construction of the Project will begin in the Spring of 2024. The first activities will be site preparation work and installation of environmental protection measures. 

​

When will construction be completed?

The project is scheduled to be complete in early 2027.

​

How will construction impact me? Will my commute be impacted?

GIP HWY 3 Inc. will minimize impacts to traffic to the extent possible and maximize safety of the traveling public throughout the construction work zone.  The sections of Highway 3 which are undergoing construction will be temporarily reduced to 60km/hr for the safety of all workers and traveling public.

​

Advanced notification of all temporary closures and lane reductions will be provided through the Project website and as E-Blasts to everyone on our Contact List.  Click here to sign up to Our Contact List and received advance notification of all closures. Please drive in accordance to the conditions, stay alert and keep a safe distance from the vehicles in front.

 

How will the public be notified of road closures?

The public will be notified of closures through the following methods:

  1. Signage in advance of and during closures

  2. Postings in the Traffic Impacts section on the project website: www.hwy3essex.com

  3. Email notices to the study’s Contact List.

 

Why are lanes closed, but I don’t see people working?

Lanes are closed for a variety of reasons such as when work is taking place, when workers gather materials and are preparing to enter to work zone, or for a safety reason.

​

What are the impacts to Side Roads?

Highway 3 is being widened from 2 to 4 lanes with a depressed grassed median. As part of the widening, Cameron Side Road/Concession Road 9, Marsh Road/Concession Road 8, Inman Side Road/South Talbot Road and Upcott Side Road will all be closed. New traffic signals will be added at Belle River Road (Essex Road 27), Essex Road 18 and Graham Side Road.  Traffic signals will also be replaced at Division Road (Essex Road 29) and Union Avenue (Essex Road 34).

 

Timing of the Side Road closures is as follows:

​

Permanent side road access closures south of Highway 3:

  • Concession Road 9 (Access at Highway 3 closed September 4, 2024);

  • Concession Road 8 (Access at Highway 3 closed September 4, 2024);

  • South Talbot Road (Access closed Summer 2025); and

  • Upcott Side Road (Access closed Summer 2025).

 

Permanent side road access closures north of Highway 3 (planned for 2026):

  • Cameron Side Road;

  • Marsh Road;

  • Inman Side Road; 

  • South Talbot Road (between Inman Side Road and Division Road [Essex Road 29]); and

  • Upcott Side Road.

 

Why is tree clearing occurring?

Clearing is the first stage of any construction project.  This will be one of the first activities to take place, and trees will be cleared in order to widen the highway. Trees will be cleared outside of nesting season to mitigate impacts to migratory birds. Otherwise trees will be reviewed by an Avian Biologist prior to removal to verify the presence of any active nesting.

 

When will the area be landscaped to replace the removed trees?

GIP HWY 3 Inc. will be developing a detailed landscape plan as part of the project’s detail design and completing all required site restoration following construction. 

 

Environmental Impacts

 

How will environmental effects be assessed and mitigated?

Appropriate mitigation measures have been recommended/developed based on the potential effects identified during previously completed and ongoing studies. All mitigation measures will be documented in Design and Construction Reports (DCRs).

​

What is being done to replace milkweed that was removed from the Highway 3 corridor during the clearing and grubbing operations?

Common Milkweed (Aeclepias syriaca) will be included in the custom native seed mix that will be used during revegetation efforts. The custom native seed mix will be applied to all disturbed areas throughout the corridor. An estimated 485, 000 square meters will be seeded to offset the loss of vegetation required for construction to proceed.

​

What is a Class Environmental Assessment?

A Class Environmental Assessment (EA) is a decision-making framework under the Ontario Environmental Assessment Act that applies to a range of similar, or class of, projects. A Class EA is used when potential environmental impacts and the proposed mitigation techniques are predictable and/or similar to other projects within that same class. MTO’s “Class EA for Provincial Transportation Facilities” document was developed in consultation with the Ministry of the Environment, and it defines and documents the process to be followed when conducting the EA study as well as requirements for public participation.

 

Was an Environmental Assessment conducted for this Project?

Yes.  In 2006, MTO completed the “Highway 3 Class Environmental Assessment Planning and Preliminary Design Study from Outer Drive Easterly to the East Junction of Essex County Road 34”, that followed the process for a Group ‘B’ project under the Class Environmental Assessment (EA) for Provincial Transportation Facilities (2000). This Study identified a strategy to accommodate transportation improvements for the Hwy 3 Corridor from 1.2km east of Essex Road 23 to 1.1km east of Essex Road 34.  The Class EA study was further documented in a 2021 Transportation Environmental Study Report (TESR 2021) Addendum, “Highway 3 Widening and Safety Enhancements Study – 1.2km East of Essex County Road 23 Easterly to 1.1km East of Essex County Road 34”.

 

Additional information on the Environmental Assessment process can be found here.

 

Does this Project have an Environmental Management System?

An Environmental Management System (EMS) has been developed to establish processes to comply with the environmental requirements of the ISO 14001:2015 Standard. The purpose of the EMS is to provide GIP HWY 3 Inc. with a framework and systematic approach to protect the environment, improve environmental performance, and illustrate continuing environmental compliance in balance with the socio-economic needs during the course of the Project.

 

What is a Design and Construction Report?

A Design and Construction Report (DCR) is the Environmental Assessment (EA) document prepared for a Group ‘B’ project under the MTO Class EA for Provincial Transportation Facilities (2000). DCRs document the EA process, design and implementation details, environmental impacts and mitigation measures, and a summary of consultation undertaken. 

​

Following completion of the DCR, and subject to obtaining required permits, approvals, and authorizations, Environmental Clearance will be issued to allow for construction of the works covered in the DCR.  Everyone on the Project Contact List will be contacted when a DCR is made available for review and comment.  Click here to sign up to Our Contact List and receive notification of all DCRs.

 

Noise Impacts

 

Where will noise walls be installed?

Noise walls will be installed during construction at the South West Quadrant of Division Road and Highway 3.

bottom of page