Contract 2

Contract 2 of the Highway 3 improvements includes the following:

​

  • Construct temporary bypass road and install temporary traffic signals at Highway 3/Victoria Avenue

  • Construct 14th Concession East Drain culvert extension on Highway 3

  • Construct Essex Outlet Drain Sewer Outlet

  • Complete Victoria Avenue Road works north of Highway 3

  • Complete Highway 3 Overpass embankment construction

  • Construct channelized island north of Highway 3 at Ellis Side Road and Highway 3

  • Construct South Talbot Road and Pinkerton Sideroad realignments

  • Construct Old South Talbot Road cul-de-sac and close South Talbot Road and Pinkerton Sideroad at Maidstone Avenue (County Road 8)

  • Construct widening of Gosfield Townline W/Arner Townline at Highway 3 intersection

  • Complete Highway 3 Eastbound lanes and culvert extensions (includes Canaan Drain, East/West Townline Drain and Russell Drain culverts).

More Information:

This page will be updated as information becomes available. 

UPDATE - MARCH 25, 2021

The 30-day public review period for DCR Contract 2 has ended. The DCR is still available on the "Project Details" page.

​

The Notice of Completion and Design and Construction Report (DCR) for Contract 2 are now available. The 30-day public review period for the DCR begins March 25, 2021, and ends April 26, 2021

​

To view the Notice of Completion and DCR, please click on the "Project Documents" button below and you will be redirected to these documents. 

​

To submit a comment or question regarding the DCR for Contract 2, please click on the "Contact Us" button below.