top of page

Photo Gallery

November 2023

Aerial footage of the Project limits, beginning at the Western limits of the Project moving easterly.

Upcott 003.JPG

August 2026

View of ongoing construction activity at Upcott Side Road on westbound lanes.

CR34 019.JPG

August 2026

View of ongoing construction activity within westbound lane area.

CR34 003.JPG

August 2026

View of traffic flow at the intersection of Essex Road 34 and Highway 3, and completed pavement activity within westbound lanes.

CR29 015.JPG

August 2026

View of new Gibbs Lane area to the north of Essex Road 29.

CR27 006.JPG

August 2026

View of completed pavement activity within westbound lane of Highway 3.

CR18 008.JPG

August 2026

View of completed line painting and pavement activity to the north of Essex Road 18, and view of completed pavement within Highway 3 westbound lane area at Essex Road 18.

Culvert N Upcott 019.JPG

July 2026

View of ongoing storm pipe placement within westbound lane area at Upcott Side Road.

Culvert Inman 003.JPG

July 2026

View of ongoing storm pipe placement within westbound lane area at Inman Side Road.

CR29 013.JPG

July 2026

View of completed construction and line painting north of Essex Road 29.

CR29 007.JPG

July 2026

View of cul-de-sac area construction north of Essex Road 29 and new paving activity within westbound lanes.

CR27 004.JPG

July 2026

View of traffic movement on new eastbound lanes and ongoing curb construction at Essex Road 18.

CR18 003.JPG

July 2026

View of traffic movement on new eastbound lanes and ongoing curb construction at Essex Road 18.

West limits 001.JPG

June 2026

View of traffic movement at the western limits of the contact.

Marsh Rd 009.JPG

June 2026

View of ongoing shoulder and median construction at Marsh Road and Highway 3.

East limits 005.JPG

June 2026

View of new pavement and markings on eastbound lanes and ongoing pavement activity near the eastern limits of the contract.

CR29 020.JPG

June 2026

New construction activity to the north of Essex Road 29.

CR27 008.JPG

June 2026

View of ongoing construction within westbound lanes at the intersection of Essex Road 27 and Highway 3.

Concession E 010.JPG

June 2026

View of ongoing construction within westbound lanes at the intersection of Essex Road 18 and Highway 3.

ER29 0003.JPG

May 2026

New pavement and line painting activity within the intersection of Essex Road 29 and Highway 3.

Graham 0008.JPG

May 2026

View of completed paving and line painting activity at the intersection of Highway 3 and Graham Side Road.

ER27 003.JPG

May 2026

Asphalt paving activity within the new Highway 3 eastbound lanes.

ER27 0018.JPG

May 2026

New asphalt pavement and concrete curb placement activity at the intersection of Highway 3 and Essex Road 34.

East Limits 0015.JPG

May 2026

Concrete curb placement and grading activity within the area of Essex Road 34 to the north and south of Highway 3.

ER18 0006.JPG

May 2026

Concrete curb placement and new line painting activity within the new Highway 3 eastbound lane and Essex Road 18 intersection.

ER29 0009.JPG

April 2026

Grading and new pavement construction to the north of Division Road (Essex Road 29).

ER29 0013.JPG

April 2026

Existing South Talbot Road and ongoing grading / paving activity within New South Talbot Road (Gibbs Lane) area.

ER34 0002.JPG

April 2026

Ongoing grading / paving / electrical and curb placement activity to the north and south of Highway 3 within the area of Essex Road 34.

ER34 0014.JPG

April 2026

Grading and curb placement activity within the area of Essex Road 34 to the south of Highway 3.

Shouldering 0001.JPG

April 2026

Placement of granular shouldering within the median ditch area of Highway 3.

Shouldering 0003.JPG

April 2026

Placement of granular shouldering within the median ditch area of Highway 3.

DJI_20251106152746_0020_V.JPG

November 2025

View of the new South Talbot Road area located to the northwest of Essex Road 29. The Blue/Green colour is seeding applications within newly excavated ditch areas. 

DJI_20251106152930_0028_V.JPG

November 2025

Ongoing grading and drainage structure installation activity within the new South Talbot Road area

DJI_20251106150024_0038_V.JPG

November 2025

View of new paved areas of Highway 3, east and west of Essex Road 18.

DJI_20251106145750_0013_V.JPG

November 2025

View of ongoing work north of Graham Side Road, temporary shifted traffic from new lanes to existing lanes.

DJI_20251106151704_0028_V.JPG

November 2025

View of closed South Talbot Road on south side of Highway 3, and paved surface to the east and west of South Talbot Road.

DJI_20251106153955_0009_V.JPG

November 2025

View of structural culvert removal and ongoing construction activity for the realignment of Concession Road 8 Drain.

ER27 Lights_0003_V.JPG

October 2025

Essex Road 27 and Highway 3 intersection with new traffic signal activation.

ER29 N Extension_0009_V.JPG

October 2025

Grading and drainage activity to the North of Essex Road 29 at South Talbot Road.

South Talbot Disconnection_0007_V.JPG

October 2025

Prepared grade for paving at South Talbot road. Disconnected South Talbot Road at Highway 3.

Upcott to Graham_0025_V.JPG

October 2025

View of new paved surface on Highway 3 at Essex Road 18 and Highway 3 intersection. 

Upcott to 34_0009_V.JPG

October 2025

View of temporary closure at Essex Road 34 to accommodate sewer structure installation on the north side of Highway 3.

Upcott to 34_0024_V.JPG

October 2025

View of ongoing sewer structure installation activity.

CR27 Sep 25 1.JPG

September 2025

Aerial view of new Essex Road 27 and new traffic signal work.

CR27 Sep 25 2.JPG

September 2025

Aerial view North of new Essex Road 27 area and drainage work.

N of 29 Sep 25 1.JPG

September 2025

Aerial view of ongoing grading work to the north of Essex Road 29.

N of 29 Sep 25 2.JPG

September 2025

Aerial view of new Essex Road 29 grading and paving activity.

35 to Graham Sep 25 2.JPG

September 2025

Aerial view of new drainage structure and grading activity to the east of Graham Road.

34 to Graham Sep 25 1.JPG

September 2025

View of ongoing drainage structure installation and grading activity at Graham Road. 

Image_20250805_172431_659.jpeg

August 2025

Photo of three Central Mudminnows (Umbra limi) relocated to suitable habitat during fish salvage activities for the extension of Structural Culvert 8, along the east branch of the No. 47 Drain.

DJI_20250710121207_0012_V_JPG.avif

July 2025

Aerial view of grading activity in progress from Essex Road 29 to South Talbot Road.

DJI_20250710121545_0032_V.JPG

July 2025

View of grading work in progress and protected drain during construction, including sediment fencing and straw bales. 

DJI_20250710121648_0041_V.JPG

July 2025

View of extended pipe culvert installation and installed riprap apron wall. 

DJI_20250710121956_0059_V.JPG

July 2025

View of grading activity, installed sewer structure and prepared ditch between Essex Road 29 and Upcott Side Road.

DJI_20250710122849_0001_V.JPG

July 2025

View of Excess Material Management Area to the east of Upcott Side Road and installed sediment fence. Grading activity in progress, Granular A top surface shown. 

image (2)_edited.jpg

July 2025

Photo of a Common Snapping Turtle (Chelydra serpentina) caught during a fish salvage and relocated to another culvert within the Project limits.

DJI_20250710123238_0014_V.JPG

July 2025

View of material placement from Upcott Side Road to Essex Road 34. 

DJI_20250602144014_0001_V.JPG

June 2025

New construction of north west branch of Essex Road 27. 

DJI_20250602144249_0012_V.JPG

June 2025

Paving and milling activity to the north branch of Essex Road 27. 

DJI_20250602145719_0001_V.JPG

June 2025

Grading activity to the south of Essex Road 29.

DJI_20250602150005_0017_V.JPG

June 2025

Grading activity to the south of Essex Road 29.

DJI_20250602150301_0006_V_JPG.avif

June 2025

Grading activity to the east of Essex Road 29. 

DJI_20250602150516_0029_V_JPG.avif

June 2025

Grading and sewer structure installation activity to the east of South Talbot Road.

DJI_20250509142734_0007_V.JPG

May 2025

Work in progress at new South Talbot Road east and west side of existing Essex Road 27. Construction in progress east of Essex Road 27.

DJI_20250509142805_0012_V.JPG

May 2025

Work in progress at new South Talbot Road east and west side of existing Essex Road 27. Construction in progress at South Talbot Road. 

DJI_20250509142948_0022_V.JPG

May 2025

​Work in progress at new South Talbot Road East and west side of existing Essex Road 27. Work in progress for culvert at Highway 3 and Essex Road 27 intersection.

DJI_20250509142642_0001_V.JPG

May 2025

Work in progress at new South Talbot Road East and west side of existing Essex Road 27. Work in progress at west limit of new Essex Road 27. 

DJI_20250509144247_0001_V.JPG

May 2025

Ditch work and new road grade work in progress to the south of Highway 3 at Essex Road 29.

DJI_20250509144432_0017_V.JPG

May 2025

Ditch work and new road grade work in progress to the south of Highway 3 at Essex Road 29. 

DJI_20250509143547_0002_V.JPG

May 2025

Work in progress for grade preparation between Essex Road 27 and Essex Road 29. 

DJI_20250509143624_0005_V.JPG

May 2025

Work in progress for grade preparation between Essex Road 27 and Essex Road 29. 

DJI_20250509144452_0018_V.JPG

May 2025

Grading work in progress for the main lane of Highway 3, between Essex Road 29 to Upcott Side Road. 

DJI_20250509144458_0020_V.JPG

May 2025

Grading work in progress for the main lane of Highway 3, between Essex Road 29 to Upcott Side Road. 

DJI_20250509144515_0024_V.JPG

May 2025

Grading work in progress for the main lane of Highway 3, between Essex Road 29 to Upcott Side Road. 

CR29Upcott_0003_V (1)_JPG.avif

April 2025

Aerial view of drainage work between Essex Road 29 and Upcott Side Road. Top view of installed culvert within roadway construction zone.

CR29TempLights_0001_V (1)_JPG.avif

April 2025

Aerial view of temporary lighting work, roadway construction, and residential noise wall work west of Essex Road 29. 

CR29Upcott_0009_V (1)_JPG.avif

April 2025

Aerial view of drainage work between Essex Road 29 and Upcott Side Road.

ER18_0002_V (1)_JPG.avif

April 2025

Aerial view of in progress construction work at Essex Road 18 area with installed concrete culverts within the roadway construction.

ER18_0007_V (1)_JPG.avif

April 2025

Aerial view of in progress construction work between Essex Road 18 and Graham Side Road.

ER18toGraham_0009_V (1)_JPG.avif

April 2025

Aerial view of in progress construction work between Essex Road 18 and Graham Side Road. View of installed concrete culverts within the roadway construction. 

Marsh_0010_V (1)_JPG.avif

April 2025

Aerial view of in progress construction activities including paving, installation of a culvert and construction of the ditch areas.

NorthCR27_0002_V (1)_JPG.avif

April 2025

Aerial view of roadway construction activity including placement of granular material and installed drainage culverts between the western limit of the Project and Concession Road 9. 

NorthCR27_0004_V (1)_JPG.avif

April 2025

Aerial view of roadway construction activity including placement of granular material and installed drainage culverts between Concession Road 9 and Concession Road 8.

excavator pic.avif

November 2024

Aerial view of grading activity and new culvert placement between Essex Road 27 and Essex Road 29.

DJI_20241106134830_0036_V_JPG.avif

November 2024

Aerial view of grading activity from west limit of construction near Barlow drain area.

road pic.avif

November 2024

Aerial view of construction in progress at Essex Road 29, top view of the noise wall near properties.

DJI_20241106130734_0025_V_JPG.avif

November 2024

​Aerial view of construction activity south of Essex Road 18. Construction activities include grading, construction of new culvert and excavation of new ditches with placement of granular material on Essex Road 18 lane areas. 

DJI_20241106130854_0038_V_JPG.avif

November 2024

Aerial view of grading activity and new ditch excavation in progress north of Essex Road 18.

DJI_20241106130932_0041_V_JPG.avif

November 2024

Aerial view of drain cleanout and grading activities north of Essex Road 18.

DJI_20241008144428_0002_V (1).JPG

October 2024

Aerial view of ongoing construction activity at Concession Road 8 and a partial view of McCain Side Road.

DJI_20241008144453_0004_V (1).JPG

October 2024

Aerial view of pavement work and grading work in progress west of Concession Road 8.

DJI_20241008144613_0011_V (1).JPG

October 2024

Aerial view of paving operation in progress west of Concession Road 8.

DJI_20241008144626_0012_V (1).JPG

October 2024

Aerial view of pavement operation in progress west of Concession Road 8.

DJI_20241008144657_0014_V (1).JPG

October 2024

Aerial view of paving activity west of Concession Road 8.

DJI_20241008144813_0021_V (1).JPG

October 2024

Aerial view of new construction activity and completed drain work at cul-de-sac area at Concession Road 9.

DJI_20240903145033_0007_V_JPG.avif

September 2024

​Aerial view of Graham Side Road electrical pole work in progress. Tree trimming occurred to accommodate installation of the electrical pole.

DJI_20240903142213_0046_V_JPG.avif

September 2024

Aerial view of cast in place culvert work and subgrade preparation work east of Concession Road 9.

DJI_20240903141649_0011_V_JPG.avif

September 2024

Aerial view of subgrade preparation and excess material management work East of Concession Road 8/McCain Side Road.

DJI_20240903141544_0007_V_JPG.avif

September 2024

Aerial view of subgrade preparation work, sediment fence and wildlife fence in place east of Concession Road 8.

DJI_20240903141509_0003_V_JPG.avif

September 2024

Aerial view of new ditch preparation work East of Concession Road 8/McCain Side Road.

1_JPG.avif

August 2024

Aerial view of select subgrade material placement from Concession Road 8 to Concession Road 9.

2_JPG.avif

August 2024

Aerial view of final subgrade elevation preparation from Concession Road 8 to Concession Road 9.

3_JPG.avif

August 2024

Aerial view of construction access way from Highway 3 and subgrade preparation work from Concession Road 8 to Concession Road 9.

4_JPG.avif

August 2024

Aerial view of cast in place culvert construction in progress on east of Concession Road 9.

5_JPG.avif

August 2024

Aerial view of removed topsoil prior to subgrade preparation work at Concession Road 9.

6_JPG.avif

August 2024

Aerial view of cast in place culvert construction work in progress on east of Concession Road 9.

1.avif

July 2024

Aerial view of new Highway 3 lane construction from 7th Concession Road Drain to Essex Road 27.

1_JPG (1).avif

July 2024

Aerial view of subgrade preparation work in progress from Concession Road 8 to Concession Road 9.

1_JPG.avif

July 2024

Aerial view of prepared subgrade at west of Essex Road 27.

2_JPG (1).avif

July 2024

Aerial view of part of subgrade preparation from Concession Road 8 to Concession Road 9.

2_JPG.avif

July 2024

Aerial view of depressed median work in progress at west of Essex Road 27.

3.avif

July 2024

Aerial view of storm water line and roadway work in progress from Concession Road 8 to Essex Road 27.

3_JPG (1).avif

July 2024

Aerial view of southern ditch preparation and borrowed material placement for subgrade preparation from Concession Road 8 to Concession Road 9.

3_JPG.avif

July 2024

Aerial view of drainage work in progress from depressed median to southern ditch at west of Essex Road 27.

4.avif

July 2024

Aerial view of subgrade preparation from Concession Road 8 to Concession Road 9.

4_JPG.avif

July 2024

Aerial view of installed wildlife fence in place at east of Essex Road 27.

IMG_1118_JPG.avif

June 2024

This image shows the soil berm separating the new ditch from the nearby drain. Sediment fencing has been installed parallel to the ditch to provide additional erosion and sediment control protection for the drain.

IMG_1154_JPG.avif

June 2024

This image shows the placement of road material over the prepared subgrade. The green-blue area to the right of the image is applied seed and cover over newly constructed ditch areas.

IMG_1679_JPG.avif

June 2024

This image shows the installed protection fencing surrounding the trees and memorial at the western limit of the Contract Limits.

IMG_1183_JPG.avif

June 2024

This image shows a portion of the wildlife protection fence (left) that was installed to prevent wildlife from entering construction zones. The sediment fence (right) protects nearby watercourses from construction sedimentation.

IMG_20240530_133848.avif

May 2024

This image shows the preparation of the subgrade following topsoil removal.

IMG_5084_JPG.avif

May 2024

This image shows the southernmost ditch construction with a view of ditch excavation and subgrade preparation east of Essex Road 27 as part of the construction staging.

bottom of page