Contract 1 of the Highway 3 improvements includes the following:

  • Installation of temporary signals at Highway 3 and Maidstone Avenue (County Road 8)

  • Construction of the second Highway 3 eastbound left turn lane at Maidstone Avenue (County Road 8)

  • Widening of Maidstone Avenue (County Road 8) and reconstruction of Highway 3/Maidstone Avenue E-N ramp

  • Relocation of sanitary and watermain crossings of Highway 3

  • Installation of Barn Swallow Kiosks and exclusionary fencing requirements for project limits

  • Construction of temporary Highway 3 roadside ditch west of Victoria Avenue

  • Installation of permanent Highway 3 property line fencing

This page will be updated as information becomes available. 

Contract 1 Overview
Work Desk

UPDATE- MARCH 2, 2021

The 30-day public review period for DCR Contract 1 has ended. The DCR is still available on the "Project Details" page.

JANUARY 28, 2021:

 

The Notice of Completion and Design and Construction Report (DCR) for Contract 1 are now available. The 30-day public review period for the DCR begins January 28, 2021, and ends March 1, 2021.

 

To view the Notice of Completion and DCR, please click on the "Project Documents" button below and you will be redirected to these documents. 

To submit a comment or question regarding the DCR for Contract 1, please

click on the "Contact Us" button below.